Dear Neighbors,

Thank you for your interest in the Takoma Park/Silver Spring Campus construction projects. We strive to keep our neighbors informed about significant construction events with this weekly email notification.

This notice will continue to provide information on the construction of the Catherine and Isiah Leggett Building construction and will now include updates regarding the HVAC rooftop replacement on Pavilions 1 and 2 (P1 and P2) and the campus library renovation in the Resource Center.

Upcoming activities are listed below:

Pavilions 1 and 2—HVAC Replacement
  • Piping Installation: The underground pipe installation is expected to be completed. The disturbed topsoil will be restored with machinery that has a backup beeper. The ground will then be seeded and mulched. Segments of the concrete walkway within the site will be repaired or replaced. Tree protection measures remain in place until this work is final.
  • Rooftop Work: With the HVAC units now in place, portions of the roof will be repaired.
  • Deliveries: Several small deliveries are expected on New York Avenue. 
Leggett Building—Construction 
  • Deliveries: Deliveries of materials are continuing to be received on site. All trucks are required to follow designated routes to and from the site and must enter and exit on Fenton Street from Philadelphia.
  • Interior Work: Work on the interior of the building is continuing to advance.
  • Saturday Work: Barton Malow will work this Saturday, August 20, beginning at 9 a.m. until 2 p.m. All work will follow the requirements of the noise ordinance.
Library/Resource Center—Renovation
  • No project updates at this time.

Please visit our website for additional information on all three TP/SS construction projects. As always, you may contact us with questions at community@montgomerycollege.edu.

Thank you,

The Montgomery College Team