Dear Neighbors,

Thank you for your interest in the Takoma Park/Silver Spring Campus construction projects. We strive to keep our neighbors informed about significant construction events with this weekly email notification.

This notice will continue to provide information on the construction of the Catherine and Isiah Leggett Building construction and will now include updates regarding the HVAC rooftop replacement on Pavilions 1 and 2 (P1 and P2) and the campus library renovation in the Resource Center.

Upcoming activities are listed below:

Pavilions 1 and 2—HVAC Replacement

  • Interior Work: Interior work related to the project will continue.
  • Dumpster Removal: The site dumpster will be removed and replaced from New York Avenue twice during the week. Vehicular and pedestrian traffic will be monitored.  
  • Saturday Work: Henley Construction will conduct interior work on Saturday, November 12. All work will follow the requirements of the noise ordinance.

Leggett Building—Construction

  • Site Utility: Excavation work is continuing for the installation of utility piping on the Fenton Street side of the structure.
  • Weather Preparation: Winter weather preparations are continuing with plastic sheets being temporarily placed on the exterior openings. Temporary heating units are being delivered and installed on site.
  • Deliveries: Materials are continuing to be delivered on site for use within the structure. All trucks are required to follow designated routes to and from the site and must enter and exit on Fenton Street from Philadelphia.
  • Interior Work: Work on the interior of the structure continues to advance.

Library/Resource Center—Renovation

  • No project updates at this time.

Please visit our website for additional information on all three TP/SS construction projects. As always, you may contact us with questions at community@montgomerycollege.edu.

Thank you,

The Montgomery College Team