Dear Neighbors, Thank you for your interest in the Takoma Park/Silver Spring Campus construction projects.…
Dear Neighbors,
Thank you for your interest in the Takoma Park/Silver Spring Campus construction projects. We strive to keep our neighbors informed about significant construction events with this weekly email notification.
This notice provides information on the construction of the Catherine and Isiah Leggett Building and the campus library renovation in the Resource Center.
Upcoming activities are listed below:
Leggett Building—Construction
- Masonry: Brick installation preparations are continuing, including waterproofing the concrete masonry wall behind the brick.
- Site Utilities: The backfilling of utility piping on the Fenton Street side of the structure is advancing.
- Interior Work: Work on the interior of the structure continues.
- Deliveries: Materials are being delivered on-site for use within the structure. All trucks are required to follow designated routes to and from the site and must enter and exit on Fenton Street from Philadelphia.
- Saturday Work: Crews will be working Saturday, March 18, between 9 a.m. and 2 p.m. to erect scaffolding for the Leggett Building greenhouse.
Library/Resource Center—Renovation
- Interior Demolition: Demolition for the interior of the building is progressing. Dumpsters have been placed inside the north and south ends of the site. Deliveries and collections will continue to take place daily.
- Abatement: Limited interior asbestos abatement work is expected to commence soon and will be in full compliance with all safety laws and regulations.
Facilities Master Plan
- Facilities Master Plan Update: Community colleges across Maryland are required by law to update their Facilities Master Plan every ten years. Montgomery College will update our plan over the coming months for the years 2023 to 2033. The master plan is a high-level document that reviews the conditions of existing facilities, future facility needs based on future enrollment, academic programs, services, and operations of the College. The updated plan is expected to be completed by the end of the year. Montgomery College will conduct community meetings to share information and to solicit your comments as we review and update the plan to meet the needs of our students and serve the residents of the county. Please watch for future notices about how to participate in these meetings.
Please visit our website for additional information on all three TP/SS construction projects. As always, you may contact us with questions at community@montgomerycollege.edu.
Thank you,
The Montgomery College Team