Thank you for your interest in the Takoma Park/Silver Spring Campus construction projects. We strive to keep our neighbors informed about significant construction events with this weekly email notification.

This notice provides information on the construction of the Catherine and Isiah Leggett Building and the campus library renovation in the Resource Center.

Upcoming activities are listed below:

Leggett Building—Construction 
  • Masonry: Scaffolding is expected to be installed on the exterior of the building for the installation of brick. 
  • Site Utilities: Utility piping backfilling on the Fenton Street side of the structure is continuing. 
  • Interior Work: Interior work within the structure is progressing. 
  • Deliveries: Materials are being delivered on site for use within the structure. All trucks are required to follow designated routes to and from the site and must enter and exit on Fenton Street from Philadelphia.
Library/Resource Center—Renovation
  • Tree Protection: Tree protection measures will be installed on site. All preparations and work on the site will be made in accordance with the College’s construction directives and in compliance with the approved tree protection plan. 
  • Fencing: Graphic coverings have been installed around the fence of the construction site to provide protection and security as well as enhance the overall aesthetics of the project area.

Please visit our website for additional information on all three TP/SS construction projects. As always, you may contact us with questions at community@montgomerycollege.edu.