Thank you for your interest in the Takoma Park/Silver Spring Campus construction projects. We strive to keep our neighbors informed about significant construction events with this email notification. As previously noted, these update emails are sent on a monthly basis.
This notice provides information on the construction of the campus library renovation in the Resource Center, the Catherine and Isiah Leggett Building, and the East Campus Garage repair for Montgomery College.
Upcoming activities and information:
Library/Resource Center—Renovation
- Utilities: This month, final electrical work for the building will be completed. This work will last for approximately two weeks and will begin December 9. A crane is no longer needed to complete this work. A backup generator will be used while the power is off in the building. As a noise reduction measure, the generator will be electric (which is less noisy than gas) and located interior to the campus. Part of the sidewalk in front of the Resource Center along New York Avenue will be closed during this work. Traffic will be reduced to one lane as needed, and flaggers will be present to assist with traffic direction.
- Move-In: Furniture is continuing to be returned to the Library/Resource Center. Final move-in items will continue through January.
- Project Completion: The project is expected to be completed in January.
Leggett Building
- Final Items: Barton Malow has a limited presence on campus to complete the final punch list of items. Any construction-related traffic is required to follow the directives regarding parking and traffic flow, including no access from Takoma Avenue. Drivers are routinely reminded they are required to follow the designated routes to and from the site and must enter and exit on Fenton Street from Philadelphia.
- Regrade of Green Space: As noted in our email to the community earlier this week, work to regrade a small area of the green space between the Leggett building and the Resource Center has been underway. This work is now complete.
East Garage
- Project Completion: Work to repair areas of the East Garage located at Fenton and King Streets is nearing completion. Until further notice, work will be conducted on Saturdays in addition to weekdays.
- Traffic on New York Avenue: AThe College offers a waiting area for pedestrians with benches and access to WiFi and parking spaces for drivers who visit campus to pick up students in the East Garage. Once the East Garage renovations are complete, it is expected that we will see an increase in the usage of these spaces. As we have done in the past, the College will communicate to our students the appropriate arrival procedures, including a reminder about the available spaces in the garage.
Please visit our website for additional information. You may contact us with questions at TPFacilitiesHelpDesk@montgomerycollege.edu or call the following numbers for any campus-related inquiries or comments: for non-urgent issues 240-567-1563, for urgent issues 240-567-3333, and for emergency situations always call 9-1-1.