skip to Main Content

Dear Neighbors,

Thank you for your interest in the Leggett Building construction project at the Takoma Park/Silver Spring Campus. We will strive to keep our neighbors informed about significant construction events with this weekly email notification.

Upcoming activities are listed below:

  • TENTATIVE – Saturday Work
    Due to the high volume of rain in past weeks, Barton Malow may conduct work this Saturday, September 11. Activities will primarily include the removal of excess soil from the site and will be actively coordinated to control truck routes. This work will take place between the hours of 9 a.m. and 2 p.m. and will follow all requirements of the noise ordinance./li>
  • Earthwork
    Cut and fill excavation for the new building footprint is nearing completion and is expected to conclude next week. This includes continued excavation and grading of the site as well as removal of the materials from excavation. As a result, the number of dump trucks traversing on Fenton Street will decrease.
  • Concrete
    This week, there will likely be a high volume of large flat-bed trucks carrying reinforcing bar deliveries to support upcoming concrete activities. The materials delivered will be staged and set up on the site. Material delivery vehicles are expected to be able to maneuver and be managed within the site, and they will enter and exit on Fenton Street.
  • Logistics
    A permit for a field office was submitted in early August. Once the permit is approved, a trailer for the construction manager’s team will be installed on site within one to two weeks.

Please visit the project’s website at montgomerycollege.edu/tpss-design for additional information. You may contact us with questions at community@montgomerycollege.edu or call the project hotline at 800-879-9879.

Thank you,

The Montgomery College Team

Back To Top