Dear Neighbors,

Thank you for your interest in the Leggett Building construction project at the Takoma Park/Silver Spring Campus. We will strive to keep our neighbors informed about significant construction events with this weekly email notification.

Upcoming activities are listed below:

  • Pile Drilling
    Pile drilling or the support of excavation will begin next week. These activities may include heavy machinery and equipment. To lessen the noise and vibration impacts, BMC will drillpiles, instead of drive piles (which is standard practice in many construction projects). This work is essential to begin excavation, which is next major activity, and will take place for the next few weeks.
  • Site Utilities
    Work on the sanitary piping and structure installation continues to progress on the east side of the project moving northwards, concurrent with the ongoing storm drain work. These activities include the use of dumpsters for material removal.
  • Earthwork
    Piping for the wells to a water tank is underway, with the intent to begin pumping water early next week. Mobilization of earthwork equipment and the sheeting and shoring equipment will take place over the next few weeks.

Please visit the project’s website at montgomerycollege.edu/tpss-design for additional information. You may contact us with questions at community@montgomerycollege.edu or call the project hotline at 800-879-9879.

Thank you,

The Montgomery College Team