Thank you for your interest in the Leggett Building construction project at the Takoma Park/Silver Spring Campus. We will strive to keep our neighbors informed about significant construction events with this weekly email notification.

Upcoming activities are listed below:

  • Fencing
    Work for the eight-foot-tall wood fence along a portion of Takoma Avenue is finishing up and will be completed in the next few days.
  • Site Utilities
    On the east side of the project, the sanitary piping and structure installation and the ongoing storm drain work continue to progress northward. These activities include the use of dumpsters for material removal.  
  • Earthwork
    Sheeting and shoring activities began last week and will continue for approximately 5-6 weeks. Excavation at the site where Falcon Hall stood is also underway to make space for the new building footprint. This will include continued excavation and grading of the site.
  • Project Update Forum
    Please join us on Tuesday, July 27, 2021, at 6 p.m. for our quarterly Project Update Forum. The Barton Malow team will share the most up-to-date information regarding the upcoming phases of construction and will be on hand to answer any questions from the public. RSVP here.

Please visit the project’s website at montgomerycollege.edu/tpss-design for additional information. You may contact us with questions at community@montgomerycollege.edu or call the project hotline at 800-879-9879.