Dear Neighbors, Thank you for your interest in the Takoma Park/Silver Spring Campus construction projects.…
Dear Neighbors,
Thank you for your interest in the Leggett Building construction project at the Takoma Park/Silver Spring Campus. We will strive to keep our neighbors informed about significant construction events with this weekly email notification.
Upcoming activities are listed below:
- Concrete Operations
Concrete floor slabs are continuing to be placed and finished within the steel structure. For more in-depth information on the concrete process, please read our concrete fact sheet. - Hauling Materials
The replacement and removal of soil is being completed when necessary. - Field Office
The installation of a field office on-site is in progress, with completion expected early next week.
Please visit the project’s website at montgomerycollege.edu/tpss-design for additional information. You may contact us with questions at community@montgomerycollege.edu or call the project hotline at 800-879-9879.
Thank you,
The Montgomery College Team