Dear Neighbors,
Thank you for your interest in the Takoma Park/Silver Spring Campus construction projects. We strive to keep our neighbors informed about significant construction events with this weekly email notification.
This notice provides information on the construction of the Catherine and Isiah Leggett Building the campus library renovation in the Resource Center, and the Facilities Master Plan work for Montgomery College.
Upcoming activities are listed below:
Leggett Building—Construction
- Takoma Ave. and Fenton Street Work: After discussions with the City of Takoma Park, Barton Malow, and the College, the WSSC work previously mentioned has progressing.
- The Takoma Avenue work has been completed and the pavement has been restored.
- Due to delays with WSSC, the work to remove the valve on Fenton Street has been postponed. We will continue to keep you updated on when this work is expected to take place. Following this, additional work on Fenton Street will be undertaken to backfill and restore the pavement. Once this has been completed, this phase of the work will be complete.
- BMC will be completing the additional work on the Takoma Avenue parking lot exit and entrance later in mid-July. Additional details about this project will be available during the upcoming Project Update Forum.
- Masonry: Work for the brick installation on the building is continuing to advance. The mason is installing brick on the Fenton Street façade.
- Roof Installation: The roof installation on the east side of the building on the second floor is continuing.
- Interior Work: Work on the interior of the structure is progressing.
- Deliveries: As previously updated, materials are being delivered on-site for use within the structure. All trucks are required to follow designated routes to and from the site and must enter and exit on Fenton Street from Philadelphia.
Library/Resource Center—Renovation
- Exterior Demolition: Exterior concrete demolition work is advancing and saw cutting measures are being utilized to manage the noise. All work will be in compliance with noise ordinances.
- Interior Work: Additional work on the interior of the building is progressing.
Facilities Master Plan
Community colleges across Maryland are required by law to update their Facilities Master Plan every ten years. Montgomery College will update our plan over the coming months for the years 2023 to 2033. For more information about the process and ways to stay engaged, please visit our website.
We look forward to seeing you at a Facilities Master Plan meeting in the fall. To view past meetings, please visit our website resources page.
Project Update Forum
You are invited to join us on Thursday, June 29, 2023, at 6 p.m. for a Project Update Forum on the Leggett Math and Science Building and the Library/Resource Center Renovation. Both project teams will share the most up-to-date information regarding the status of the projects and an overview of upcoming work. They will be on hand to answer any questions from the public. In addition, an update on the Facilities Master Plan process will be provided. Please RSVP here.
Please visit our website for additional information on all three TP/SS construction projects. As always, you may contact us with questions at community@montgomerycollege.edu or call the project hotline at 800-879-9879.
Thank you,
The Montgomery College Team