Thank you for your interest in the Takoma Park/Silver Spring Campus construction projects. We strive to keep our neighbors informed about significant construction events with this weekly email notification.

This notice provides information on the construction of the Catherine and Isiah Leggett Building and the campus library renovation in the Resource Center.

Upcoming activities are listed below:

Leggett Building—Construction 
  • Upcoming Takoma Ave. Work: As previously noted, work is expected to occur in May for the creation of the south parking lot entrance/exit on Takoma Ave. This long-planned lot will serve a limited number of vehicles. Truck traffic specific only to the parking lot completion and partial road closures are expected on Takoma Ave. for the duration of this work. All work will be conducted in line with construction directives and will prioritize minimizing disruption in the area. More information will be provided soon.
  • Masonry: The brick installation for the building is continuing to advance.
  • Greenhouse: The installation of the greenhouse on the south end of the building is nearing completion. 
  • Site Utilities: Backfilling of utility piping on the Fenton Street side of the structure is continuing. 
  • Interior Work: The interior building work is continuing. 
  • Deliveries: Materials are being delivered on-site for use within the structure. All trucks are required to follow designated routes to and from the site and must enter and exit on Fenton Street from Philadelphia. 
Facilities Master Plan
  • Facilities Master Plan Update: Community colleges across Maryland are required by law to update their Facilities Master Plan every ten years. Montgomery College will update our plan over the coming months for the years 2023 to 2033. The master plan is a high-level document that reviews the conditions of existing facilities, future facility needs based on future enrollment, academic programs, services, and operations of the College. The updated plan is expected to be completed by the end of the year. Montgomery College will conduct community meetings to share information and to solicit your comments as we review and update the plan to meet the needs of our students and serve the residents of the county.
  • Community Meetings: Two collegewide public meetings will be held between now and the end of fall, along with additional engagement sessions for specific campus locations. Following the first collegewide Facilities Master Plan public meeting, a meeting will be held for Takoma Park/Silver Spring residents. The collegewide kickoff will be held on May 2 at 6pm and the meeting for Takoma Park/Silver Spring residents will be held May 4 at 6pm (please register here). 
Library/Resource Center—Renovation
  • Interior Demolition: Demolition work for the project is continuing to advance. Dumpsters are present on the north and south ends of the site. Deliveries and collections will continue to take place daily. 
  • Asbestos Removal: Exterior asbestos abatement work will commence the week of May 8. All work will be in full compliance with all safety laws and regulations.
  • Interior Work: Additional work on the interior of the building has commenced. 
Pedestrian Bridge Construction
  • Brawner Builders has completed the necessary repairs on the bearing plates on the pedestrian bridge.

Please visit our website for additional information on all three TP/SS construction projects. As always, you may contact us with questions at community@montgomerycollege.edu.