Dear Neighbors,

Below you will find a series of activities you can expect to take place in the next two weeks.

Updates include:

  • Utility work: Utility installation is underway. This involves layout, sawcutting, pavement removal, and earth work activities. The storm drains near the Commons Building will be laid out by the site utility contractor. These activities will include new equipment and materials deliveries, and the use of dumpsters for material removal.
  • Tree protection and removal: We will continue tree removal including cutting, grinding, chipping of trees under 4” in diameter, and removing stumps as needed. Additional tree protection and erosion and sediment control measures will be installed. These activities will include new equipment and materials deliveries, as well as the use of dumpsters for material removal. You can find our tree projection plan on the Resources page of the project website.
  • Demolition: Soft demolition is underway, meaning non-structural demolition materials are being removed. In the next two weeks, structural demolition could kick off, meaning the exterior walls may be removed and heavy machinery will be on site. For more information on our noise mitigation procedures, visit the project website.
  • Holiday schedule: Our team will be off for the Christmas and New Year’s holiday. Work will not occur and the project site will be quiet on 12/24, 12/25, 12/31 and 1/1/2021. Best wishes for a happy holiday!

If you have any questions, please contact community@montgomerycollege.eduor call the project hotline at 800-879-9879.

Thank you,
The Montgomery College Team